Skip to main content

City of Auburn Water Treatment Plant Improvements

Location
Ohio
Market
Federal Government
Services
Architecture / Interior Design / Engineering

The Challenge

In 1934, Building 23 at Wright-Patterson Air Force Base was constructed as an aircraft hangar and test facility. More than 70 years later, the U.S. Air Force wanted to renovate the building to provide a modern lab facility for state-of-the-art energy research. It requested a design that retains the historic feel and aesthetic of the original building, while also creating a modern interior that meets security and force protection requirements.

The Solution

A three-story facility was created within the existing brick shell, adding new spaces for material processing, data acquisition, operations, and fabrication. The design also had special acoustical needs due to the use of vibration-sensitive equipment such as lasers and optical equipment. The superstructure is composed of a structural steel frame and designed to resist collapse in accordance with Antiterrorism/Force Protection (AT/FP) requirements.

Barge Design Solutions provided HVAC, plumbing, steam, lighting and power distribution, communications and security, utilities, storm drainage, lighting protection, and fire protection. Site work included sidewalks, curbs and gutters, access drive control systems, and site upgrades to meet AT/FP requirements. Architectural and interior design were also included as part of the project.

The Impact

The renovation of Building 23 was a testament to Barge's engineering expertise and commitment to excellence. Barge successfully transformed a historic asset into a modern, sustainable, and secure facility, meeting the evolving needs of the U.S. Air Force. The team's ability to balance preservation with innovation while also prioritizing sustainability and security positioned Barge as a valuable partner in this critical project. The project exceeded the original goal of designing to a LEED Silver level, making it the first LEED Gold building on the base.

The Challenge

Auburn’s James Estes Water Treatment Plant was originally constructed in the 1960s and had a capacity of 8 million gallons per day (MGD). To meet growth demands, the City of Auburn wanted to increase capacity by 50% to 12 MGD. Due to budget constraints, the City decided to phase the expansion of the plant by making modifications to different components over time, based on need. The phasing of the construction activity and completion time was critical due to the need to have the plant at full capacity during construction.

The Solution

Barge Design Solutions began by renovating settling basins and replacing mechanisms that were installed with the original construction. It also repaired basin walls, including repairing leaks and sealing cracks in the basin floor. A protective coating was also installed on internal basin walls to extend the life of the basin concrete.

The next phase involved removing five existing liquid chemical tanks and installing four new larger tanks and containment structures, all without interrupting plant operations.

The final phase involved increasing the storage capacity by abandoning one clearwell and demolishing a second clearwell to make room for a new 500,000-gallon in-ground reservoir. New pumps were installed, and existing pumps on a third clearwell were replaced to increase pumping capacity. As part of the upgrade, an existing pump room was converted into a dedicated electrical room.

The Result

The Barge team's expertise in water treatment plant design and construction enabled the successful expansion of the James Estes Water Treatment Plant. Their ability to balance the need for increased capacity with the constraints of budget and operational continuity demonstrates their commitment to delivering sustainable and reliable water infrastructure solutions.

Engineering
Water
No items found.
City of Auburn Water Treatment Plant Improvements
Consult with an Expert
Thank you!
Your message has been submitted
Oops! Something went wrong while submitting the form.

We're collaborative by design. Let's team up.

Begin your project development journey today by contacting us.